SMASD projects completed, gym renovation delayed

August 12, 2014

Photo by Amy Cherry Crews are shown installing ceiling tiles inside the SSMSE Kelly Gym.

This summer proved busy for maintenance staff at St. Marys Area School District. There were several large capital projects which were completed including renovations to South St. Marys Street Elementary's gymnasium.
"The Kelly Gym project was going well until Friday," according to Mark Romain, SMASD director of facilities.
The project hit a roadblock when Romain was informed the new windows have not shipped and will not arrive until Labor Day. Crews were expecting the windows to arrive by Aug. 11.
"The new windows have left other parts of the project in limbo," Romain said.

The Elk County Catholic Crusader soccer team defeated the St. Marys Area Flying Dutchmen 1-0 on...
Being down 2-0 early in Tuesday afternoon's game did little to phase the St. Marys Area Lady Dutch...
The St. Marys Area Lady Dutch volleyball squad won their third straight match last night as they...
On March 14, 2012, Governor Tom Corbett signed into law a contentious piece of legislation...